The Board of Directors of Segovia 21, SA, in a meeting held today, June 23, has agreed to award the construction works of the 18-hole golf course “La Faisanera” to the Temporary Joint Venture –UTE– formed by VOLCONSA and MADRILEÑA DE RIEGOS, SA.
The contract was awarded for €11,059,202, which includes overhead costs and VAT. This represents a reduction of 22.071% compared to the initial bid price.
The deadline committed by the joint venture for the complete execution of the works and making them available to the owner has been 15 months, which is 3 months less than those foreseen in the tender (18)
Extensive experience in golf course construction
The Board of Directors particularly valued Madrileña de Riegos' extensive experience in building large and important golf courses. The company has demonstrated its construction of more than 29 golf courses in the last 10 years, located in various regions of Spain, the Canary Islands, Portugal, and elsewhere.
Field maintenance for two years
The award also entails the obligation on the part of the joint venture to carry out the full maintenance of the field during the first two years of operation, and all this based on demanding parameters of quality, training and job creation in the area (at least fifteen new jobs are expected), environmental assessment of the surroundings based on the content of the Environmental Impact Statement, etc., and all this within the indicated award price.
The public tender for the work
A total of 21 companies submitted bids for the project, one of which was rejected from the outset for lacking the classification from the Ministry of Economy and Finance, required for this project.
As previously reported, the tendering process for these works was conducted in accordance with the regulations of the Public Administrations Contracts Law, and was subsequently published on April 8th in the Official Journal of the European Union (OJEU), as well as in the Official Gazette of the Province.
Signing of contracts and start of works
In the coming days, the corresponding contracts will be signed, and the initial site survey work will begin. Construction is expected to commence in July or August and be completed by the end of 2009. This would allow the field to be inaugurated, with optimal conditions for planting stability and the installation of facilities, in the first months of 2010.
The future golf course is located on a 603,000 m2 plot designated for “sports facilities” within the “Quitapesares” Partial Plan, situated on the Segovia-San Ildefonso road, in the municipality of Palazuelos de Eresma. In this same area, Segovia 21 is simultaneously developing the first business park in the province of Segovia (buildings for offices, research, a business and training center, a business incubator, a commercial area, hotels, sports facilities, residential areas, etc., covering an area of over 430,000 m2).
The golf course project, the first 18-hole course in the province, has been designed by the renowned professional player, José María Olazábal, and the prestigious sports architecture firm, Integral Golf Design –IGD– directed by José Luis Bastarreche, and aims to be, due to its design and features, a benchmark course for golf in the central area of Spain.